Owner
State University Construction Fund
353 Broadway
Albany, NY 12246
Engineer
Jacobs Engineering
5 Penn Plaza, 18th Floor
New York, NY
Contract Amount
$1.72 million
Scope of Work
This project required the removal and replacement of 6,385 linear feet of granite curb, removal of 21,300 square feet of concrete sidewalks, installation of 13,565 square feet of new concrete sidewalk, removal and replacement of 244,653 square feet of asphalt pavement, installation of 320 linear feet of sanitary sewer, 1,630 linear feet of 12″-18″ storm sewer & 220 linear feet of 48″ RCP storm sewer, and the installation of new light poles and the corresponding electrical conduit.